CONSTRUCTION OF ROAD, BARANGAY SAN LEONARDO, MARIA AURORA, AURORA
Location
Maria Aurora, Aurora
Central Luzon
ZIP: 3202
15.777800, 121.468000
Project Cost
₱13M
₱13,441,445.16
Project Timeline
Start Date
March 10, 2025
Mon, Mar 10, 2025
Actual Start
March 10, 2025
Mon, Mar 10, 2025
Target Completion
June 14, 2025
Sat, Jun 14, 2025
Source of Fund
1 source
General Appropriations Act FY 2025
Implementing Agency
1 agency
Contractor
1 contractor