ROAD WIDENING - TERTIARY ROADS, BUENAVISTA-BUNAGUIT RD - K1259 + 000 - K1260 + 000, K1262 + 327 - K1263 + 000
Location
Buenavista, Agusan Del Norte
Caraga
8.974500, 125.409100
Project Cost
₱46M
₱45,973,779.43
Project Timeline
Start Date
February 12, 2025
Wed, Feb 12, 2025
Actual Start
February 12, 2025
Wed, Feb 12, 2025
Target Completion
August 27, 2025
Wed, Aug 27, 2025
Source of Fund
1 source
General Appropriations Act FY 2025
Implementing Agency
1 agency
Contractor
1 contractor