REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD., K1042+000 - K1042+170, K1043+250 - K1043+540, K1043+660 - K1043+831
Location
Naval, Biliran
Eastern Visayas
11.576819, 124.395069
Project Cost
₱49M
₱48,965,120.5
Project Timeline
Start Date
March 03, 2025
Mon, Mar 03, 2025
Actual Start
March 03, 2025
Mon, Mar 03, 2025
Target Completion
October 18, 2025
Sat, Oct 18, 2025
Source of Fund
1 source
General Appropriations Act FY 2025
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...