NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD, K1050+900 - K1051+890, K1052+867-K1053+970
Location
Naval, Biliran
Eastern Visayas
11.576819, 124.395069
Project Cost
₱77M
₱77,105,985.4
Project Timeline
Start Date
March 03, 2025
Mon, Mar 03, 2025
Actual Start
March 03, 2025
Mon, Mar 03, 2025
Target Completion
December 17, 2025
Wed, Dec 17, 2025
Source of Fund
1 source
General Appropriations Act FY 2025
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates