Laoag-Sarrat-Piddig-Solsona Rd - K0488 + 380 - K0489 + 449, K0489 + 977 - K0489 + 1017, K0490 + 157 - K0490 + 826, K0491 + 133 - K0491 + 553, K0492 + 060 - K0492 + 207, K0492 + 247.30 - K0492 + 248, K0492 + 326 - K0492 + 386, K0493 + 576 - K0497 + 130, K0499 + 000 - K0499 + 442, K0499 + 697 - K0499 + 713, K0499 + 763 - K0499 + 855, K0500 + 000 - K0502 + 301, K0502 + 412 - K0502 + 1009, K0503 + 017 - K0503 + 754, K0503 + 845 - K0503 + 848, K0503 + 894 - K0503 + 936, K0503 + 940 - K0504 + 149, K0504 + 223 - K0504 + 239, K0504 + 300 - K0505 + 147, K0505 + 236 - K0507 + 395, K0507 + 420.10 - K0508 + 000
Location
Bagbag, Solsona, Ilocos Norte
Ilocos Region
ZIP: 0
18.114546, 120.753970
Project Cost
₱260M
₱263,125,000.0
Project Timeline
Start Date
February 23, 2025
Sun, Feb 23, 2025
Actual Start
February 23, 2025
Sun, Feb 23, 2025
Target Completion
November 11, 2025
Tue, Nov 11, 2025
Source of Fund
1 source
General Appropriations Act FY 2025
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...