Jct (TNR) Cortes-Balilihan-Catigbian-Macaas Rd - K0010 + 299 - K0010 + 323, K0014 + 798 - K0014 + 855, K0015 + 028 - K0015 + 050, K0015 + 291 - K0015 + 384, K0018 + 125 - K0018 + 153, K0040 + 160 - K0040 + 226, K0045 + 981 - K0046 + 000, K0046 + 153 - K0046 + 195
Location
Cortes, Bohol
Central Visayas
ZIP: 0
9.850000, 124.033300
Project Cost
₱4.5M
₱4,540,000.0
Project Timeline
Start Date
May 14, 2025
Wed, May 14, 2025
Actual Start
May 14, 2025
Wed, May 14, 2025
Target Completion
August 16, 2025
Sat, Aug 16, 2025
Source of Fund
1 source
General Appropriations Act FY 2025
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project