Construction of Flood Control Structures along Sinidman River (Upstream) Phase II, Brgy. Sinidman Occidental, Calbayog City, Samar
Location
Sinidman Occidental, City of Calbayog, Samar
Eastern Visayas
ZIP: 6710
12.145520, 124.564700
Project Cost
₱49M
₱48,603,252.0
Project Timeline
Start Date
February 07, 2022
Mon, Feb 07, 2022
Actual Start
February 07, 2022
Mon, Feb 07, 2022
Target Completion
September 27, 2022
Tue, Sep 27, 2022
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet