Construction of Flood Control Structure along Binahaan River, Brgy. Cogon, Palo, Leyte
Location
Cogon, Palo, Leyte
Eastern Visayas
ZIP: 6501
11.143010, 125.001700
Project Cost
₱49M
₱48,950,000.0
Project Timeline
Start Date
March 27, 2023
Mon, Mar 27, 2023
Actual Start
March 27, 2023
Mon, Mar 27, 2023
Target Completion
June 21, 2023
Wed, Jun 21, 2023
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close