Construction of Tunga Flood Control Structure and Drainage system, Tunga River Basin, Barangay Astorga, Tunga, Leyte
Location
Astorga, Tunga, Leyte
Eastern Visayas
ZIP: 6503
11.256480, 124.764700
Project Cost
₱55M
₱55,209,716.0
Project Timeline
Start Date
April 25, 2023
Tue, Apr 25, 2023
Actual Start
April 25, 2023
Tue, Apr 25, 2023
Target Completion
April 12, 2024
Fri, Apr 12, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor