Construction of Subang Daku Flood Control (San Isidro Section), Sogod, Southern Leyte
Location
San Isidro, Sogod, Southern Leyte
Eastern Visayas
ZIP: 6606
10.415100, 124.994800
Project Cost
₱19M
₱19,299,932.0
Project Timeline
Start Date
September 10, 2023
Sun, Sep 10, 2023
Actual Start
September 10, 2023
Sun, Sep 10, 2023
Target Completion
March 27, 2024
Wed, Mar 27, 2024
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project