Construction of Sta. Sofia Flood Control, Padre Burgos, Southern Leyte
Location
Padre Burgos, Southern Leyte
Eastern Visayas
ZIP: 6612
10.027900, 125.018400
Project Cost
₱62M
₱61,683,588.0
Project Timeline
Start Date
March 12, 2024
Tue, Mar 12, 2024
Actual Start
March 12, 2024
Tue, Mar 12, 2024
Target Completion
November 14, 2024
Thu, Nov 14, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates