Construction of Flood Control Project, Gandara, Samar
Location
Gandara, Samar
Eastern Visayas
ZIP: 6706
12.017100, 124.812900
Project Cost
₱20M
₱19,761,388.0
Project Timeline
Start Date
May 09, 2023
Tue, May 09, 2023
Actual Start
May 09, 2023
Tue, May 09, 2023
Target Completion
July 10, 2024
Wed, Jul 10, 2024
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project