Construction of Jubas Flood Control, Libagon, Southern Leyte
Location
Libagon, Southern Leyte
Eastern Visayas
ZIP: 6615
10.363130, 125.170700
Project Cost
₱20M
₱19,568,360.0
Project Timeline
Start Date
February 09, 2022
Wed, Feb 09, 2022
Actual Start
February 09, 2022
Wed, Feb 09, 2022
Target Completion
November 18, 2022
Fri, Nov 18, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor