Construction of Flood Control Structure along Gandara River, Barangay Bulao, San Jorge, Samar
Location
Bulao, San Jorge, Samar
Eastern Visayas
ZIP: 6707
11.980680, 124.854200
Project Cost
₱49M
₱48,947,871.0
Project Timeline
Start Date
April 25, 2024
Thu, Apr 25, 2024
Actual Start
April 25, 2024
Thu, Apr 25, 2024
Target Completion
November 10, 2024
Sun, Nov 10, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close