Construction (Completion) of Storm Surge Protection: Tide Embankment, Section 5, Phase 7, Brgy. Calogcog, Tanauan, Leyte
Location
Calogcog, Tanauan, Leyte
Eastern Visayas
ZIP: 6502
11.126390, 125.019300
Project Cost
₱17M
₱17,154,778.0
Project Timeline
Start Date
February 27, 2022
Sun, Feb 27, 2022
Actual Start
February 27, 2022
Sun, Feb 27, 2022
Target Completion
August 09, 2022
Tue, Aug 09, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor