Rehabilitation of Bulawan Flood Control, San Francisco Section, Malilipot, Albay
Location
San Francisco, Malilipot, Albay
Bicol Region
ZIP: 4510
13.309866, 123.761272
Project Cost
₱43M
₱43,120,000.0
Project Timeline
Start Date
August 04, 2022
Thu, Aug 04, 2022
Actual Start
August 04, 2022
Thu, Aug 04, 2022
Target Completion
March 31, 2023
Fri, Mar 31, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates