Construction of Soa (Upstream) River Control, Malinao, Albay
Location
Soa, Malinao, Albay
Bicol Region
ZIP: 4512
13.203122, 123.392644
Project Cost
₱49M
₱49,000,000.0
Project Timeline
Start Date
August 09, 2022
Tue, Aug 09, 2022
Actual Start
August 09, 2022
Tue, Aug 09, 2022
Target Completion
November 29, 2022
Tue, Nov 29, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project