Project Cost
₱96M
₱96,499,331.17
Project Timeline
Start Date
November 30, 2021
Tue, Nov 30, 2021
Actual Start
November 30, 2021
Tue, Nov 30, 2021
Target Completion
September 01, 2022
Thu, Sep 01, 2022
Source of Fund
1 source
General Appropriations Act FY 2021
Implementing Agency
1 agency
Contractor
1 contractor