Construction of Flood Control Structure along Pawa River, Brgy. Pawa, Matnog, Sorsogon
Location
Pawa, Matnog, Sorsogon
Bicol Region
ZIP: 4708
12.607544, 124.058888
Project Cost
₱49M
₱48,999,966.52
Project Timeline
Start Date
February 17, 2022
Thu, Feb 17, 2022
Actual Start
February 17, 2022
Thu, Feb 17, 2022
Target Completion
March 20, 2023
Mon, Mar 20, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...