Rehabilitation/Improvement of Flood Mitigation at Bulawan River, Irosin, Sorsogon
Location
Bulawan, Irosin, Sorsogon
Bicol Region
ZIP: 4707
12.729658, 123.963822
Project Cost
₱95M
₱95,380,291.78
Project Timeline
Start Date
February 14, 2022
Mon, Feb 14, 2022
Actual Start
February 14, 2022
Mon, Feb 14, 2022
Target Completion
April 15, 2023
Sat, Apr 15, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor