Construction of Flood Mitigation Structure along Budiao-Busay River (Phase 2), Sta. 1 + 000 - Sta. 1 + 220, Daraga, Albay
Location
Busay, Daraga, Albay
Bicol Region
ZIP: 4501
13.166536, 123.702401
Project Cost
₱49M
₱48,998,161.04
Project Timeline
Start Date
June 29, 2022
Wed, Jun 29, 2022
Actual Start
June 29, 2022
Wed, Jun 29, 2022
Target Completion
December 25, 2022
Sun, Dec 25, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project