Rehabilitation/Improvement of Joroan Flood Control (Upstream and Downstream of Joroan Bridge #1 and Bridge #2 ), Tiwi, Albay
Location
Joroan, Tiwi, Albay
Bicol Region
ZIP: 4513
13.491423, 123.620544
Project Cost
₱120M
₱120,624,912.8
Project Timeline
Start Date
February 14, 2022
Mon, Feb 14, 2022
Actual Start
February 14, 2022
Mon, Feb 14, 2022
Target Completion
December 07, 2022
Wed, Dec 07, 2022
Source of Fund
1 source
General Appropriations Act FY 2021
Implementing Agency
1 agency
Contractor
1 contractor