Construction of Revetment, Sta. 3+596 to Sta. 3+713, Barangay Malubago, Sipocot, Camarines Sur
Location
Malubago, Sipocot, Camarines Sur
Bicol Region
ZIP: 4408
13.770420, 122.978900
Project Cost
₱30M
₱29,699,691.66
Project Timeline
Start Date
March 23, 2022
Wed, Mar 23, 2022
Actual Start
March 23, 2022
Wed, Mar 23, 2022
Target Completion
November 09, 2022
Wed, Nov 09, 2022
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project