Construction of River Bank Protection along Baclayon River (Phase 1), Labanon Section, Barangay Basud, Bacacay, Albay
Location
Basud, Bacacay, Albay
Bicol Region
ZIP: 4509
13.279318, 123.796061
Project Cost
₱20M
₱19,600,000.0
Project Timeline
Start Date
August 24, 2022
Wed, Aug 24, 2022
Actual Start
August 24, 2022
Wed, Aug 24, 2022
Target Completion
January 26, 2023
Thu, Jan 26, 2023
Source of Fund
1 source
General Appropriations Act FY 2022
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close