Construction of Flood Mitigation Structure along Basag River (Upstream of Spillway facing Left And Right Side ), Barangay Basag, Ligao City, Albay.
Location
Basag, City of Ligao, Albay
Bicol Region
ZIP: 4504
13.258564, 123.592443
Project Cost
₱97M
₱96,500,000.0
Project Timeline
Start Date
March 20, 2024
Wed, Mar 20, 2024
Actual Start
March 20, 2024
Wed, Mar 20, 2024
Target Completion
August 30, 2024
Fri, Aug 30, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates