Construction of Joroan River Control (Downstream), Tiwi, Albay
Location
Joroan, Tiwi, Albay
Bicol Region
ZIP: 4513
13.491789, 123.618852
Project Cost
₱39M
₱39,200,000.0
Project Timeline
Start Date
February 12, 2024
Mon, Feb 12, 2024
Actual Start
February 12, 2024
Mon, Feb 12, 2024
Target Completion
July 20, 2024
Sat, Jul 20, 2024
Source of Fund
1 source
General Appropriations Act FY 2024
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project