Construction of Flood Control Structure (along Cut-off Channel), Brgy. Irayang Solong, Minalabac, Camarines Sur
Location
Irayang Solong, Minalabac, Camarines Sur
Bicol Region
ZIP: 4414
13.566304, 123.177570
Project Cost
₱96M
₱96,447,416.6
Project Timeline
Start Date
February 16, 2023
Thu, Feb 16, 2023
Actual Start
February 16, 2023
Thu, Feb 16, 2023
Target Completion
October 16, 2023
Mon, Oct 16, 2023
Project Location Map
Location Map
Source of Fund
1 source
General Appropriations Act FY 2023
Implementing Agency
1 agency
Contractor
1 contractor
Project Updates
Updates
(0)
No updates yet
Be the first to share an update about this project
Project Updates
1 / 1
Use arrow keys to navigate • Press Esc to close
Loading comments...