Back
Contractor Profile
TOPNOTCH CATALYST BUILDERS INC.
Government Contractor Profile & Statistics
Total Projects
50
Total Value
₱2.8B
₱2,825,621,662.32
Avg. Cost
₱57M
Avg. Progress
N/A
Project Status Distribution
Completed
49 projects
(98.0%)
Incomplete
1 projects
(2.0%)
Contract Value by Status
Completed
₱2.8B
₱2,776,622,367.0
Incomplete
₱49M
₱48,999,295.32
Yearly Statistics
| Year | Projects | Total Value | Average Cost |
|---|---|---|---|
| 2024 | 19 |
₱1.4B ₱1,355,972,524.63 |
₱71M |
| 2023 | 16 |
₱790M ₱794,635,934.02 |
₱50M |
| 2022 | 15 |
₱680M ₱675,013,203.67 |
₱45M |
Projects by Region
Central Luzon
42 projects₱2.5B
₱2,472,335,988.5
NCR
8 projects₱350M
₱353,285,673.82
Top 10 Provinces
1
42
Bulacan
₱2.5B
₱2,472,335,988.5
Top 10 Projects by Contract Value
1
Construction of Riverbank Protection Structure along Angat River, Barangay Lumang Bayan, Plaridel, Bulacan
P00821268LZ
Completed
Lumang Bayan, Plaridel, Bulacan
₱96M
₱96,499,699.7
2
Construction of Riverbank Protection Structure at Barangay Pritil, Guiguinto, Bulacan
P00838408LZ
Completed
Pritil, Guiguinto, Bulacan
₱96M
₱96,499,556.14
3
Construction of Riverbank Protection Structure at Barangay Bunsuran, Pandi, Bulacan
P00838391LZ
Completed
Pandi, Bulacan
₱96M
₱96,499,509.1
4
Construction of Slope Protection Along Taguig River, Facing Downstream (East Bank), Package 2, Taguig City
P00620047LZ
Completed
Hagonoy, City of Taguig
₱96M
₱96,499,365.4
5
Construction of Riverbank Protection Structure at Barangay Bunsuran (Phase II), Pandi, Bulacan
P00838390LZ
Completed
Pandi, Bulacan
₱96M
₱96,499,112.67
6
Construction of Riverbank Protection Structure at Barangay Tilapayong, Baliuag, Bulacan
P00838418LZ
Completed
Tilapayong, Baliuag, Bulacan
₱96M
₱96,498,805.78
7
Rehabilitation of Major River System with Flood Control Structure at Bulusan, Calumpit, Bulacan
P00620203LZ
Completed
Bulusan, Calumpit, Bulacan
₱91M
₱91,467,153.21
8
Construction of Riverbank Protection Structure at Barangay Sapang Bayan, Calumpit, Bulacan
P00838416LZ
Completed
Sapang Bayan, Calumpit, Bulacan
₱77M
₱77,199,865.91
9
Construction of Reinforced Concrete Flood Control Structure along Angat River, Culianin Section (Purok 2), Plaridel, Bulacan
P00825072LZ
Completed
Culianin, Plaridel, Bulacan
₱77M
₱77,199,815.33
10
Construction of Reinforced Concrete Flood Control Structure along Angat River, Bintog Section, Plaridel, Bulacan
P00825070LZ
Completed
Bintog, Plaridel, Bulacan
₱77M
₱77,199,741.94
Projects by Type
Main Portal
50 projects
₱2.8B
Comments & Discussion