Total Projects
9
Total Value
₱95M
₱95,031,440.44
Avg. Cost
₱11M
Avg. Progress
N/A
Project Status Distribution
Completed
9 projects
(100.0%)
Contract Value by Status
Completed
₱95M
₱95,031,440.44
Yearly Statistics
| Year | Projects | Total Value | Average Cost |
|---|---|---|---|
| 2024 | 1 |
₱29M ₱29,400,000.0 |
₱29M |
| 2023 | 4 |
₱44M ₱44,073,954.5 |
₱11M |
| 2022 | 4 |
₱22M ₱21,557,485.94 |
₱5.4M |
Projects by Region
Central Visayas
2 projects₱49M
₱49,000,000
Eastern Visayas
3 projects₱20M
₱19,721,817
Ilocos Region
1 project₱9.7M
₱9,650,000
BARMM
1 project₱6.9M
₱6,860,609.84
Bicol Region
1 project₱4.9M
₱4,948,753.5
Central Luzon
1 project₱4.9M
₱4,850,260.1
Top 10 Provinces
1
2
Cebu
₱49M
₱49,000,000
2
1
Southern Leyte
₱9.9M
₱9,875,201
3
2
Eastern Samar
₱9.8M
₱9,846,616
4
1
Ilocos Norte
₱9.7M
₱9,650,000
5
1
Lanao Del Sur
₱6.9M
₱6,860,609.84
6
1
Catanduanes
₱4.9M
₱4,948,753.5
7
1
Nueva Ecija
₱4.9M
₱4,850,260.1
Top 10 Projects by Contract Value
1
Construction of Flood Control Structure at Magsa-ubay Bridge, Daanbantayan, Cebu
P00820187VS
Completed
Daanbantayan, Cebu
₱29M
₱29,400,000.0
2
Construction of Flood Control Structure at Magsa-ubay Bridge, Section 1 and 2, Sta. 000 + 000 - Sta. 000 + 306, Daanbantayan, Cebu
P00721669VS
Completed
Poblacion, Daanbantayan, Cebu
₱20M
₱19,600,000.0
3
Construction of Seawall, Brgy. Pinut-an, San Ricardo, Southern Leyte
P00733710VS
Completed
Pinut-an, San Ricardo, Southern Leyte
₱9.9M
₱9,875,201.0
4
Construction/Improvement of Flood Control Structure along Cayubog Creek, Paoay, Ilocos Norte
P00726852LZ
Completed
Cayubog, Paoay, Ilocos Norte
₱9.7M
₱9,650,000.0
5
Construction of Flood Control along Pagayawan Road, Barangay Banago, Balabagan, Lanao de Sur
P00634128MN
Completed
Banago, Balabagan, Lanao Del Sur
₱6.9M
₱6,860,609.84
6
Construction of River Control at Barangay Malobago, Maydolong, Eastern Samar
P00630678VS
Completed
Malobago, Maydolong, Eastern Samar
₱4.9M
₱4,949,995.0
7
Construction of River Control Dike at Bagumbayan, Bato, Catanduanes
P00737572LZ
Completed
Bagumbayan, Bato, Catanduanes
₱4.9M
₱4,948,753.5
8
Rehabilitation of Drainage System at Brgy. Sabang South, Borongan City, Eastern Samar
P00620183VS
Completed
Sabang South, City of Borongan, Eastern Samar
₱4.9M
₱4,896,621.0
9
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY CULAYLAY, SAN JOSE, NUEVA ECIJA
22CE0038
Completed
San Jose City, Nueva Ecija
₱4.9M
₱4,850,260.1
Projects by Type