Back
Contractor Profile
MG SAMIDAN CONSTRUCTION / RM30 PSG CONSTRUCTION CORPORATION
Government Contractor Profile & Statistics
Total Projects
4
Total Value
₱300M
₱298,684,479.3
Avg. Cost
₱75M
Avg. Progress
N/A
Project Status Distribution
Completed
4 projects
(100.0%)
Contract Value by Status
Completed
₱300M
₱298,684,479.3
Yearly Statistics
| Year | Projects | Total Value | Average Cost |
|---|---|---|---|
| 2023 | 2 |
₱170M ₱173,745,720.9 |
₱87M |
| 2022 | 2 |
₱120M ₱124,938,758.4 |
₱62M |
Projects by Region
CAR
4 projects₱300M
₱298,684,479.3
Top 10 Provinces
1
4
Abra
₱300M
₱298,684,479.3
Top 10 Projects by Contract Value
1
Construction of Naguillan Flood Control Structure, La Paz, Abra
P00740307LZ
Completed
La Paz, Abra
₱140M
₱144,747,500.0
2
Construction of Flood Control Structure, Barangay Mudeng, La Paz, Abra
P00639320LZ
Completed
Mudeng, La Paz, Abra
₱95M
₱95,238,758.4
3
Construction of Bugbog-Santa Rosa Flood Control Structure (Phase 2), Barangay Bugbog to Barangay Santa Rosa, Bucay, Abra
P00632759LZ
Completed
Bugbog, Bucay, Abra
₱30M
₱29,700,000.0
4
Construction of Flood Control Structure, Barangay Banbancag, Bucay, Abra
P00639439LZ
Completed
Bucay, Abra
₱29M
₱28,998,220.9
Projects by Type
Main Portal
4 projects
₱300M
Comments & Discussion
Loading comments...