Total Projects
3
Total Value
₱24M
₱24,174,184.52
Avg. Cost
₱8.1M
Avg. Progress
N/A
Project Status Distribution
Completed
3 projects
(100.0%)
Contract Value by Status
Completed
₱24M
₱24,174,184.52
Yearly Statistics
| Year | Projects | Total Value | Average Cost |
|---|---|---|---|
| 2024 | 3 |
₱24M ₱24,174,184.52 |
₱8.1M |
Projects by Region
CALABARZON
3 projects₱24M
₱24,174,184.52
Top 10 Provinces
1
3
Laguna
₱24M
₱24,174,184.52
Top 10 Projects by Contract Value
1
Rehabilitation of Revetment along San Isidro River, Barangay Riverside, City of San Pedro, Laguna
P00820385LZ
Completed
Riverside, City of San Pedro, Laguna
₱14M
₱14,473,182.52
2
Construction of Drainage Canal System, Barangay Landayan, San Pedro, Laguna
P00839622LZ
Completed
Landayan, City of San Pedro, Laguna
₱4.9M
₱4,864,617.0
3
Construction of Drainage Canal along Laguna Resettlement Community School going to Magsaysay, Barangay United Bayanihan, San Pedro, Laguna
P00839630LZ
Completed
United Bayanihan, City of San Pedro, Laguna
₱4.8M
₱4,836,385.0