Total Projects
5
Total Value
₱300M
₱304,593,190.39
Avg. Cost
₱61M
Avg. Progress
N/A
Project Status Distribution
Completed
5 projects
(100.0%)
Contract Value by Status
Completed
₱300M
₱304,593,190.39
Yearly Statistics
| Year | Projects | Total Value | Average Cost |
|---|---|---|---|
| 2024 | 1 |
₱90M ₱89,565,038.74 |
₱90M |
| 2023 | 3 |
₱190M ₱185,328,151.65 |
₱62M |
| 2022 | 1 |
₱30M ₱29,700,000.0 |
₱30M |
Projects by Region
NCR
4 projects₱270M
₱274,893,190.39
CALABARZON
1 project₱30M
₱29,700,000
Top 10 Provinces
1
1
Rizal
₱30M
₱29,700,000
Top 10 Projects by Contract Value
1
Construction of Flood Control Wall along the Banks of Creeks, Barangay 176 Phase 9, Caloocan City
P00820045LZ
Completed
City of Caloocan
₱90M
₱89,565,038.74
2
Construction of Flood Control Structure along the Banks of Creeks, Barangay 160, Caloocan City (Phase 2)
P00725541LZ
Completed
City of Caloocan
₱85M
₱84,678,409.32
3
Construction of Flood Mitigation Structure (Installation of Automatic Trash Screen) at Maya Creek, Barangay Rizal, Makati City
P00725531LZ
Completed
Rizal, City of Makati
₱61M
₱61,469,424.33
4
Construction of Box Culvert with Revetment along Coastal Road (San Dionisio Section, Phase II), Parañaque City
P00727011LZ
Completed
La Huerta, City of Parañaque
₱39M
₱39,180,318.0
5
Construction of Slope Protection Structure, Barangay Lubo, Jala-jala, Rizal
P00632919LZ
Completed
Lubo, Jala-Jala, Rizal
₱30M
₱29,700,000.0
Projects by Type
Main Portal
5 projects
₱300M