Total Projects
4
Total Value
₱200M
₱203,942,655.48
Avg. Cost
₱51M
Avg. Progress
N/A
Project Status Distribution
Completed
4 projects
(100.0%)
Contract Value by Status
Completed
₱200M
₱203,942,655.48
Yearly Statistics
| Year | Projects | Total Value | Average Cost |
|---|---|---|---|
| 2023 | 1 |
₱57M ₱57,419,383.62 |
₱57M |
| 2022 | 3 |
₱150M ₱146,523,271.86 |
₱49M |
Projects by Region
Central Luzon
4 projects₱200M
₱203,942,655.48
Top 10 Provinces
1
4
Tarlac
₱200M
₱203,942,655.48
Top 10 Projects by Contract Value
1
Construction of Slope Protection with Steel Sheet Pile Foundation along Tarlac River Control Left Dike, San Isidro - Sta Maria Section, Tarlac City, Tarlac (Package D)
P00742133LZ
Completed
San Isidro, City of Tarlac, Tarlac
₱57M
₱57,419,383.62
2
Construction of Slope Protection along Camiling River (Left Bank), Anoling 2nd - Pao 3rd Section (Package D), Camiling, Tarlac
P00640526LZ
Completed
Anoling 2nd, Camiling, Tarlac
₱50M
₱49,500,000.0
3
Construction of Slope Protection along Camiling River (Left Bank), Pindangan 1st - Pindangan 2nd Section (Package D), Camiling, Tarlac
P00640527LZ
Completed
Pindangan 2nd, Camiling, Tarlac
₱49M
₱48,511,637.23
4
Construction of Slope Protection along Tarlac River Control (Right Dike), Colibangbang Section (Package A), Paniqui, Tarlac
P00640528LZ
Completed
Colibangbang, Paniqui, Tarlac
₱49M
₱48,511,634.63