Government Contractor Profile & Statistics
Total Projects
5
Total Value
₱490M
₱486,558,563.83
Avg. Cost
₱97M
Avg. Progress
N/A
Project Status Distribution
Completed
1 projects
(20.0%)
Ongoing
4 projects
(80.0%)
Contract Value by Status
Ongoing
₱390M
₱390,058,563.83
Completed
₱97M
₱96,500,000.0
Yearly Statistics
| Year | Projects | Total Value | Average Cost |
|---|---|---|---|
| 2024 | 4 |
₱390M ₱390,058,563.83 |
₱98M |
| 2022 | 1 |
₱97M ₱96,500,000.0 |
₱97M |
Projects by Region
Zamboanga Peninsula
4 projects₱390M
₱390,058,563.83
Central Visayas
1 project₱97M
₱96,500,000
Top 10 Provinces
1
4
Zamboanga Del Sur
₱390M
₱390,058,563.83
2
1
Cebu
₱97M
₱96,500,000
Top 10 Projects by Contract Value
1
SIPAG - FLOOD MITIGATION STRUCTURES - PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF WATER TREATMENT PLANT FACILITY WITH FLOODGATE & PUMPING STATION, CATCHMENT 1 (PHASE 3), ZAMBOANGA CITY
24J00145
Ongoing
City of Zamboanga, Zamboanga Del Sur
₱140M
₱144,648,540.47
2
Construction of Flood Control Structure along Cansaga River, Barangay Danglag, Consolacion, Cebu
P00620025VS
Completed
Danglag, Consolacion, Cebu
₱97M
₱96,500,000.0
3
SIPAG - FLOOD MITIGATION STRUCTURES - PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF WATER TREATMENT PLANT FACILITY WITH FLOODGATE & PUMPING STATION, CATCHMENT 1 (PHASE 2), ZAMBOANGA CITY
24J00144
Ongoing
City of Zamboanga, Zamboanga Del Sur
₱96M
₱96,396,875.23
4
CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY DIVERSION ROAD, PACKAGE 8, ZAMBOANGA CITY
24J00014
Ongoing
City of Zamboanga, Zamboanga Del Sur
₱91M
₱91,220,642.95
5
CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - ZAMBOANGA CITY BY-PASS ROAD, PACKAGE 5, ZAMBOANGA CITY
24J00048
Ongoing
City of Zamboanga, Zamboanga Del Sur
₱58M
₱57,792,505.18
Projects by Type
Main Portal
5 projects
₱490M